Changes between Version 10 and Version 11 of PublicPages/Schedule


Ignore:
Timestamp:
Feb 20, 2019 6:55:00 PM (6 years ago)
Author:
David Schlegel
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • PublicPages/Schedule

    v10 v11  
    66- 2019-01-25 - Primary mirror re-aluminization complete and back on telescope
    77- 2019-02-11 - Start functional verification of two spectrographs at KPNO
    8 - 2019-02-15 - Install second spectrograph on rack at Mayall Telescope (line 681)
    9 - 2019-03-13 - Fiber View Camera (FVC) installation (line 338)
     8- 2019-02-15 - Install second spectrograph on rack at Mayall Telescope
     9- 2019-03-08 - Fiber View Camera (FVC) installation and start verification (line 338)
    1010- 2019-03-15 - Imaging Surveys DR8 release
    11 - 2019-04-01 - Commissioning Instrument available to commissioning team (line 368)
    12 - 2019-05-16 - End of CI run (6 weeks long, line 368)
     11- 2019-03-28 - Commissioning Instrument available to commissioning team (line 368)
     12- 2019-05-15 - End of CI run (6 weeks long, line 368)
    1313- 2019-07-15 - Imaging Surveys DR9 release
    14 - 2019-09-09 - Commissioning start with focal plane + spectrographs (First Light, line 618, "Telescope ready")
     14- 2019-09-04 - Commissioning start with focal plane + spectrographs (First Light, line 618, "Telescope ready")
    1515- 2019-10-01 - Last spectrograph installed (line 642, "Install Spectrographs")
    16 - 2020-01-11 - Nominal start of Survey Validation
     16- 2020-01-12 - Nominal start of Survey Validation (line 833)
    1717
    18 Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 3 Feb 2019.
     18Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 16 Feb 2019.