12 | | - 2019-03-08 - Fiber View Camera (FVC) installation and start verification (line 338) |
13 | | - 2019-03-15 - Imaging Surveys DR8 release |
14 | | - 2019-03-28 - Commissioning Instrument available to commissioning team (line 368) |
15 | | - 2019-05-15 - End of CI run (6 weeks long, line 368) |
| 12 | - 2019-03-13 - Fiber View Camera (FVC) installation and start verification (line 339) |
| 13 | - 2019-03-25 - Imaging Surveys DR8 release |
| 14 | - 2019-03-28 - Commissioning Instrument available to commissioning team (line 366) |
| 15 | - 2019-05-15 - End of CI run (6 weeks long, line 366) |
17 | | - 2019-09-04 - Commissioning start with focal plane + spectrographs (First Light, line 618, "Telescope ready") |
18 | | - 2019-10-01 - Last spectrograph installed (line 642, "Install Spectrographs") |
19 | | - 2020-01-12 - Nominal start of Survey Validation (line 833) |
| 17 | - 2019-09-05 - Commissioning start with focal plane + spectrographs (First Light, line 620, "Telescope ready") |
| 18 | - 2019-10-01 - Last spectrograph installed (line 644, "Install Spectrographs") |
| 19 | - 2020-01-12 - Nominal start of Survey Validation (line 903) |