Changes between Version 12 and Version 13 of PublicPages/Schedule


Ignore:
Timestamp:
Feb 25, 2019 9:18:54 AM (6 years ago)
Author:
David Schlegel
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • PublicPages/Schedule

    v12 v13  
    1010== Near-future milestones ==
    1111
    12 - 2019-03-08 - Fiber View Camera (FVC) installation and start verification (line 338)
    13 - 2019-03-15 - Imaging Surveys DR8 release
    14 - 2019-03-28 - Commissioning Instrument available to commissioning team (line 368)
    15 - 2019-05-15 - End of CI run (6 weeks long, line 368)
     12- 2019-03-13 - Fiber View Camera (FVC) installation and start verification (line 339)
     13- 2019-03-25 - Imaging Surveys DR8 release
     14- 2019-03-28 - Commissioning Instrument available to commissioning team (line 366)
     15- 2019-05-15 - End of CI run (6 weeks long, line 366)
    1616- 2019-07-15 - Imaging Surveys DR9 release
    17 - 2019-09-04 - Commissioning start with focal plane + spectrographs (First Light, line 618, "Telescope ready")
    18 - 2019-10-01 - Last spectrograph installed (line 642, "Install Spectrographs")
    19 - 2020-01-12 - Nominal start of Survey Validation (line 833)
     17- 2019-09-05 - Commissioning start with focal plane + spectrographs (First Light, line 620, "Telescope ready")
     18- 2019-10-01 - Last spectrograph installed (line 644, "Install Spectrographs")
     19- 2020-01-12 - Nominal start of Survey Validation (line 903)
    2020
    21 Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 16 Feb 2019.
     21Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 23 Feb 2019.