    1010== Near-future milestones ==
    1111
    12 - 2019-03-13 - Fiber View Camera (FVC) installation and start verification (line 339)
     12- 2019-03-11 - Fiber View Camera (FVC) installation and start verification (line 341)
    1313- 2019-03-25 - Imaging Surveys DR8 release
    14 - 2019-03-28 - Commissioning Instrument available to commissioning team (line 366)
    15 - 2019-05-15 - End of CI run (6 weeks long, line 366)
     14- 2019-04-01 - Start of Commissioning Instrument (CI) run (line 372)
     15- 2019-05-17 - End of CI run (6 weeks long, line 372)
    1616- 2019-07-15 - Imaging Surveys DR9 release
    17 - 2019-09-05 - Commissioning start with focal plane + spectrographs (First Light, line 620, "Telescope ready")
    18 - 2019-10-01 - Last spectrograph installed (line 644, "Install Spectrographs")
    19 - 2020-01-12 - Nominal start of Survey Validation (line 903)
     17- 2019-09-12 - Commissioning start with focal plane + spectrographs (First Light, line 627, "Telescope ready")
     18- 2019-10-01 - Last spectrograph installed (line 651, "Install Spectrographs")
     19- 2020-01-12 - Nominal start of Survey Validation (line 910)
    2020
    21 Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 23 Feb 2019.
     21Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 9 Mar 2019.