    1010- 2019-03-14 - Telescope motion enabled  [https://desi.lbl.gov/trac/tracmailman/browser/private/desi-daylog/2019-March/000320.html (daylog)]
    1111- 2019-03-20 - Imaging Surveys dr8b release
    12 
     12- 2019-04-01 - Start of Commissioning Instrument (CI) run (line 381)
    1313
    1414== Near-future milestones ==
    1515
    16 - 2019-04-01 - Start of Commissioning Instrument (CI) run (line 381)
    17 - 2019-04-15 - Imaging Surveys DR8 release
    18 - 2019-05-17 - End of CI run (6 weeks long, line 381)
    19 - 2019-07-15 - Imaging Surveys DR9 release
    20 - 2019-09-13 - Commissioning start with focal plane + spectrographs (First Light, line 687, "Telescope ready")
    21 - 2019-10-01 - Last spectrograph installed (line 711, "Install Spectrographs")
    22 - 2019-12-02 - Initial Survey Validation fields (line 959)
    23 - 2020-01-12 - Nominal start of Survey Validation (line 970)
     16- 2019-04-30 - Imaging Surveys DR8 release
     17- 2019-05-16 - End of CI run (6 weeks long, line 381)
     18- 2019-09-16 - Commissioning start with focal plane + spectrographs (First Light, line 693, "Telescope ready")
     19- 2019-10-01 - Last spectrograph installed (line 717, "Install Spectrographs")
     20- 2019-10-15 - Imaging Surveys DR9 release (TBD)
     21- 2019-12-03 - Initial Survey Validation fields (line 964)
     22- 2020-01-12 - Nominal start of Survey Validation (line 975)
    2423
    25 Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 24 Mar 2019.
     24Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 1 Apr 2019.