Changes between Version 21 and Version 22 of PublicPages/Schedule


Ignore:
Timestamp:
May 6, 2019 10:18:35 AM (6 years ago)
Author:
David Schlegel
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • PublicPages/Schedule

    v21 v22  
    1010- 2019-03-14 - Telescope motion enabled  [https://desi.lbl.gov/trac/tracmailman/browser/private/desi-daylog/2019-March/000320.html (daylog)]
    1111- 2019-03-20 - Imaging Surveys dr8b release
    12 - 2019-04-01 - Start of Commissioning Instrument (CI) run (line 381)
     12- 2019-04-01 - Start of Commissioning Instrument (CI) run
     13- 2019-05-06 - Pause in CI run to move cage
    1314
    1415== Near-future milestones ==
    1516
    16 - 2019-05-16 - End of CI run (6 weeks long)
     17- 2019-05-17 - Resume CI run (could be as early as 05-15 depending on progress)
    1718- 2019-05-31 - Imaging Surveys DR8 release
    18 - 2019-09-12 - Commissioning start with focal plane + spectrographs (First Light, line 697, "Telescope ready")
    19 - 2019-10-17 - Last spectrograph installed (line 732, "Install Spectrographs")
     19- 2019-06-03 - End of CI run
     20- 2019-09-23 - Commissioning start with focal plane + spectrographs (First Light, line 701, "Telescope ready")
     21- 2019-10-17 - Last spectrograph installed (line 725, "Install Spectrographs")
    2022- 2019-10-15 - Imaging Surveys DR9 release (TBD)
    21 - 2019-12-10 - Initial Survey Validation fields (line 980)
    22 - 2020-01-12 - Nominal start of Survey Validation (line 991)
     23- 2019-12-10 - Initial Survey Validation fields (line 974)
     24- 2020-01-12 - Nominal start of Survey Validation (line 985)
    2325
    2426Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 28 Apr 2019.