    1212- 2019-04-01 - Start of Commissioning Instrument (CI) run
    1313- 2019-05-06 - Pause in CI run to move cage
     14- 2019-05-15 - Resume CI run
    1415
    1516== Near-future milestones ==
    1617
    17 - 2019-05-15 - Resume CI run
    1818- 2019-05-31 - Imaging Surveys DR8 release
    1919- 2019-06-03 - End of CI run
    20 - 2019-09-20 - Commissioning start with focal plane + spectrographs (First Light, line 696, "Telescope ready")
    21 - 2019-10-17 - Last spectrograph installed (line 720, "Install Spectrographs")
     20- 2019-09-23 - Commissioning start with focal plane + spectrographs (First Light, line 697, "Telescope ready")
     21- 2019-10-17 - Last spectrograph installed (line 721, "Install Spectrographs")
    2222- 2019-10-15 - Imaging Surveys DR9 release (TBD)
    23 - 2019-12-07 - Initial Survey Validation fields (line 972)
    24 - 2020-01-12 - Nominal start of Survey Validation (line 983)
     23- 2019-12-10 - Initial Survey Validation fields (line 973)
     24- 2020-01-12 - Nominal start of Survey Validation (line 984)
    2525
    26 Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 11 May 2019.
     26Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 18 May 2019.