    v25 v26  
    1818
    1919- 2019-06-17 - Imaging Surveys DR8 release
    20 - 2019-09-27 - Commissioning start with focal plane + spectrographs (First Light, line 706, "Telescope ready")
    21 - 2019-10-17 - Last spectrograph installed (line 730, "Install Spectrographs")
     20- 2019-10-01 - Commissioning start with focal plane + spectrographs (First Light, line 707, "Telescope ready")
     21- 2019-10-17 - Last spectrograph installed (line 731, "Install Spectrographs")
    2222- 2019-10-15 - Imaging Surveys DR9 release (TBD)
    23 - 2019-12-14 - Initial Survey Validation fields (line 982)
    24 - 2020-01-12 - Nominal start of Survey Validation (line 993)
     23- 2019-12-18 - Initial Survey Validation fields (line 983)
     24- 2020-01-12 - Nominal start of Survey Validation (line 994)
    2525
    26 Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 1 June 2019.
     26Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 4 June 2019.