    1919- 2019-07-01 - Imaging Surveys DR8 release
    20 - 2019-10-01 - Commissioning start with focal plane + spectrographs (First Light, line 712, "Telescope ready")
    21 - 2019-10-29 - Last spectrograph installed (line 736, "Install Spectrographs")
     20- 2019-09-26 - Commissioning start with focal plane + spectrographs (First Light, line 714, "Telescope ready")
     21- 2019-10-29 - Last spectrograph installed (line 737, "Install Spectrographs")
    2222- 2019-10-15 - Imaging Surveys DR9 release (TBD)
    23 - 2019-12-18 - Initial Survey Validation fields (line 991)
    24 - 2020-01-12 - Nominal start of Survey Validation (line 1002)
     23- 2019-12-13 - Initial Survey Validation fields (line 993)
     24- 2020-01-12 - Nominal start of Survey Validation (line 1004)
    2525
    26 Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 22 June 2019.
     26Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 28 June 2019.