    1818== Near-future milestones ==
    1919
    20 - 2019-09-25 - Commissioning start with focal plane + spectrographs (First Light, line 715, "Telescope ready")
    21 - 2019-10-29 - Last spectrograph installed (line 739, "Install Spectrographs")
     20- 2019-09-27 - Commissioning start with focal plane + spectrographs (First Light, line 719, "Telescope ready")
     21- 2019-10-29 - Last spectrograph installed (line 743, "Install Spectrographs")
    2222- 2019-10-15 - Imaging Surveys DR9 release (TBD)
    23 - 2019-12-12 - Initial Survey Validation fields (line 992)
    24 - 2020-01-12 - Nominal start of Survey Validation (line 1003)
     23- 2019-12-14 - Initial Survey Validation fields (line 996)
     24- 2020-01-12 - Nominal start of Survey Validation (line 1007)
    2525
    2626Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 5 July 2019.