Changes between Version 30 and Version 31 of PublicPages/Schedule
- Timestamp:
- Jul 14, 2019 6:23:12 PM (5 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
PublicPages/Schedule
v30 v31 18 18 == Near-future milestones == 19 19 20 - 2019-09-2 5 - Commissioning start with focal plane + spectrographs (First Light, line 715, "Telescope ready")21 - 2019-10-29 - Last spectrograph installed (line 7 39, "Install Spectrographs")20 - 2019-09-27 - Commissioning start with focal plane + spectrographs (First Light, line 719, "Telescope ready") 21 - 2019-10-29 - Last spectrograph installed (line 743, "Install Spectrographs") 22 22 - 2019-10-15 - Imaging Surveys DR9 release (TBD) 23 - 2019-12-1 2 - Initial Survey Validation fields (line 992)24 - 2020-01-12 - Nominal start of Survey Validation (line 100 3)23 - 2019-12-14 - Initial Survey Validation fields (line 996) 24 - 2020-01-12 - Nominal start of Survey Validation (line 1007) 25 25 26 26 Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 5 July 2019.