    1818== Near-future milestones ==
    1919
    20 - 2019-09-27 - Commissioning start with focal plane + spectrographs (First Light, line 719, "Telescope ready")
    21 - 2019-12-16 - Last spectrograph installed (line 763, "Install Spectrographs")
     20- 2019-10-10 - Commissioning start with focal plane + spectrographs (First Light, line 740, "Telescope ready")
     21- 2019-11-26 - Last spectrograph installed (line 778, "Install Spectrographs")
    2222- 2019-12-01 - Imaging Surveys DR9 release
    23 - 2019-12-14 - Initial Survey Validation fields (line 996)
    24 - 2020-01-12 - Nominal start of Survey Validation (line 1007)
     23- 2019-12-27 - Initial Survey Validation fields (line 1039)
     24- 2020-01-12 - Nominal start of Survey Validation (line 1050)
    2525
    26 Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 17 Aug 2019.
     26Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 23 Aug 2019.