Changes between Version 37 and Version 38 of PublicPages/Schedule
- Timestamp:
- Sep 8, 2019 1:31:16 PM (5 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
PublicPages/Schedule
v37 v38 18 18 == Near-future milestones == 19 19 20 - 2019-10-1 0 - Commissioning start with focal plane + spectrographs (First Light, line 746, "Telescope ready")21 - 2019-11-26 - Last spectrograph installed (line 78 4, "Install Spectrographs")20 - 2019-10-16 - Commissioning start with focal plane + spectrographs (First Light, line 749, "Telescope ready") 21 - 2019-11-26 - Last spectrograph installed (line 787, "Install Spectrographs") 22 22 - 2019-12-01 - Imaging Surveys DR9 release 23 - 20 19-12-27 - Initial Survey Validation fields (line 1045)24 - 2020-01-12 - Nominal start of Survey Validation (line 10 56)23 - 2020-01-02 - Initial Survey Validation fields (line 1051) 24 - 2020-01-12 - Nominal start of Survey Validation (line 1062) 25 25 26 26 Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 2 Sep 2019.