Changes between Version 37 and Version 38 of PublicPages/Schedule


Ignore:
Timestamp:
Sep 8, 2019 1:31:16 PM (5 years ago)
Author:
David Schlegel
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • PublicPages/Schedule

    v37 v38  
    1818== Near-future milestones ==
    1919
    20 - 2019-10-10 - Commissioning start with focal plane + spectrographs (First Light, line 746, "Telescope ready")
    21 - 2019-11-26 - Last spectrograph installed (line 784, "Install Spectrographs")
     20- 2019-10-16 - Commissioning start with focal plane + spectrographs (First Light, line 749, "Telescope ready")
     21- 2019-11-26 - Last spectrograph installed (line 787, "Install Spectrographs")
    2222- 2019-12-01 - Imaging Surveys DR9 release
    23 - 2019-12-27 - Initial Survey Validation fields (line 1045)
    24 - 2020-01-12 - Nominal start of Survey Validation (line 1056)
     23- 2020-01-02 - Initial Survey Validation fields (line 1051)
     24- 2020-01-12 - Nominal start of Survey Validation (line 1062)
    2525
    2626Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 2 Sep 2019.