    2121- 2019-11-26 - Last spectrograph installed (line 787, "Install Spectrographs")
    2222- 2019-12-01 - Imaging Surveys DR9 release
    23 - 2020-01-02 - Initial Survey Validation fields (line 1051)
    24 - 2020-01-12 - Nominal start of Survey Validation (line 1062)
     23- 2020-02-26 - End of commissioning, start of Survey Validation (4.5 months after line 749, from project plan in monthly report)
    2524
    26 Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 2 Sep 2019.
     25Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 2 Sep 2019. (start of SV taken from Monthly Report)