Changes between Version 38 and Version 39 of PublicPages/Schedule
- Timestamp:
- Sep 12, 2019 8:55:51 AM (5 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
PublicPages/Schedule
v38 v39 21 21 - 2019-11-26 - Last spectrograph installed (line 787, "Install Spectrographs") 22 22 - 2019-12-01 - Imaging Surveys DR9 release 23 - 2020-01-02 - Initial Survey Validation fields (line 1051) 24 - 2020-01-12 - Nominal start of Survey Validation (line 1062) 23 - 2020-02-26 - End of commissioning, start of Survey Validation (4.5 months after line 749, from project plan in monthly report) 25 24 26 Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 2 Sep 2019. 25 Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 2 Sep 2019. (start of SV taken from Monthly Report)