    33== Near-future milestones ==
    44
    5 - 2019-01-14 - Primary mirror re-aluminization complete and back on telescope (line 269)
    6 - 2019-01-28 - Begin installation of spectrographs + cryostats at the Mayall Telescope (line 638)
     5- 2019-01-24 - Primary mirror re-aluminization complete and back on telescope (line 269)
     6- 2019-01-28 - Begin installation of spectrographs + cryostats at the Mayall Telescope (line 646)
    77- 2019-02-11 - Start functional verification of two spectrographs at KPNO
    88- 2019-02-15 - Imaging Surveys DR8 release
    9 - 2019-02-28 - Fiber View Camera (FVC) installation (line 337)
    10 - 2019-03-26 - Commissioning Instrument available to commissioning team (CI First Light, line 361)
    11 - 2019-05-06 - End of CI run (6 weeks long, line 361)
     9- 2019-03-11 - Fiber View Camera (FVC) installation (line 338)
     10- 2019-04-01 - Commissioning Instrument available to commissioning team ( line 360)
     11- 2019-05-13 - End of CI run (6 weeks long, line 361)
    1212- 2019-07-15 - Imaging Surveys DR9 release
    13 - 2019-09-04 - Commissioning start with focal plane + spectrographs (First Light, line 582)
    14 - 2019-10-01 - Last spectrograph installed (line 609)
     13- 2019-09-20 - Commissioning start with focal plane + spectrographs (First Light, line 598)
     14- 2019-10-08 - Last spectrograph installed (line 618)
    1515- 2020-01-11 - Nominal start of Survey Validation
    1616