    33== Near-future milestones ==
    44
     5- 2019-01-11 - Install first spectrograph on rack at Mayall Telescope (line 656)
    56- 2019-01-24 - Primary mirror re-aluminization complete and back on telescope (line 269)
    6 - 2019-01-28 - Begin installation of spectrographs + cryostats at the Mayall Telescope (line 646)
    77- 2019-02-11 - Start functional verification of two spectrographs at KPNO
     8- 2019-02-15 - Install second spectrograph on rack at Mayall Telescope (line 677)
    89- 2019-02-15 - Imaging Surveys DR8 release
    910- 2019-03-11 - Fiber View Camera (FVC) installation (line 338)
    10 - 2019-04-01 - Commissioning Instrument available to commissioning team ( line 360)
    11 - 2019-05-13 - End of CI run (6 weeks long, line 361)
     11- 2019-04-01 - Commissioning Instrument available to commissioning team (line 365)
     12- 2019-05-16 - End of CI run (6 weeks long, line 365)
    1213- 2019-07-15 - Imaging Surveys DR9 release
    13 - 2019-09-20 - Commissioning start with focal plane + spectrographs (First Light, line 598)
    14 - 2019-10-08 - Last spectrograph installed (line 618)
     14- 2019-09-06 - Commissioning start with focal plane + spectrographs (First Light, line 615, "Telescope ready")
     15- 2019-10-08 - Last spectrograph installed (line 639, "Install Spectrographs")
    1516- 2020-01-11 - Nominal start of Survey Validation
    1617
    17 Activities at Kitt Peak updated from DESI-4550 on 13 Jan 2019.
     18Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 21 Jan 2019.