  • PublicPages/Schedule

    v8 v9  
    44
    55- 2019-01-11 - Install first spectrograph on rack at Mayall Telescope (line 656)
    6 - 2019-01-24 - Primary mirror re-aluminization complete and back on telescope (line 269)
     6- 2019-01-25 - Primary mirror re-aluminization complete and back on telescope (line 269)
    77- 2019-02-11 - Start functional verification of two spectrographs at KPNO
    8 - 2019-02-15 - Install second spectrograph on rack at Mayall Telescope (line 677)
    9 - 2019-02-15 - Imaging Surveys DR8 release
    10 - 2019-03-11 - Fiber View Camera (FVC) installation (line 338)
    11 - 2019-04-01 - Commissioning Instrument available to commissioning team (line 365)
    12 - 2019-05-16 - End of CI run (6 weeks long, line 365)
     8- 2019-02-15 - Install second spectrograph on rack at Mayall Telescope (line 678)
     9- 2019-03-11 - Fiber View Camera (FVC) installation (line 337)
     10- 2019-03-15 - Imaging Surveys DR8 release
     11- 2019-04-02 - Commissioning Instrument available to commissioning team (line 365)
     12- 2019-05-17 - End of CI run (6 weeks long, line 365)
    1313- 2019-07-15 - Imaging Surveys DR9 release
    14 - 2019-09-06 - Commissioning start with focal plane + spectrographs (First Light, line 615, "Telescope ready")
    15 - 2019-10-08 - Last spectrograph installed (line 639, "Install Spectrographs")
     14- 2019-09-09 - Commissioning start with focal plane + spectrographs (First Light, line 615, "Telescope ready")
     15- 2019-10-01 - Last spectrograph installed (line 639, "Install Spectrographs")
    1616- 2020-01-11 - Nominal start of Survey Validation
    1717
    18 Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 21 Jan 2019.
     18Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 26 Jan 2019.