= Schedule = == Past milestones == - 2019-01-11 - Install first spectrograph on rack at Mayall Telescope - 2019-01-25 - Primary mirror re-aluminization complete and back on telescope - 2019-02-11 - Start functional verification of two spectrographs at KPNO - 2019-02-15 - Install second spectrograph on rack at Mayall Telescope - 2019-03-11 - Fiber View Camera (FVC) installation [https://desi.lbl.gov/trac/tracmailman/browser/private/desi-daylog/2019-March/000316.html (daylog)] - 2019-03-14 - Telescope motion enabled [https://desi.lbl.gov/trac/tracmailman/browser/private/desi-daylog/2019-March/000320.html (daylog)] - 2019-03-20 - Imaging Surveys dr8b release - 2019-04-01 - Start of Commissioning Instrument (CI) run (line 381) == Near-future milestones == - 2019-04-30 - Imaging Surveys DR8 release - 2019-05-16 - End of CI run (6 weeks long) - 2019-09-12 - Commissioning start with focal plane + spectrographs (First Light, line 691, "Telescope ready") - 2019-10-01 - Last spectrograph installed (line 715, "Install Spectrographs") - 2019-10-15 - Imaging Surveys DR9 release (TBD) - 2019-12-02 - Initial Survey Validation fields (line 962) - 2020-01-12 - Nominal start of Survey Validation (line 973) Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 5 Apr 2019.