wiki:PublicPages/Schedule

Version 17 (modified by David Schlegel, 6 years ago) (diff)

--

Schedule

Past milestones

  • 2019-01-11 - Install first spectrograph on rack at Mayall Telescope
  • 2019-01-25 - Primary mirror re-aluminization complete and back on telescope
  • 2019-02-11 - Start functional verification of two spectrographs at KPNO
  • 2019-02-15 - Install second spectrograph on rack at Mayall Telescope
  • 2019-03-11 - Fiber View Camera (FVC) installation (daylog)
  • 2019-03-14 - Telescope motion enabled (daylog)
  • 2019-03-20 - Imaging Surveys dr8b release

Near-future milestones

  • 2019-04-01 - Start of Commissioning Instrument (CI) run (line 377)
  • 2019-04-15 - Imaging Surveys DR8 release
  • 2019-05-17 - End of CI run (6 weeks long, line 377)
  • 2019-07-15 - Imaging Surveys DR9 release
  • 2019-09-11 - Commissioning start with focal plane + spectrographs (First Light, line 673, "Telescope ready")
  • 2019-10-01 - Last spectrograph installed (line 697, "Install Spectrographs")
  • 2019-12-02 - Initial Survey Validation fields (line 945)
  • 2020-01-12 - Nominal start of Survey Validation (line 956)

Activities at Kitt Peak updated from DESI-4550 on 20 Mar 2019.