Schedule
Past milestones
- 2019-01-11 - Install first spectrograph on rack at Mayall Telescope
- 2019-01-25 - Primary mirror re-aluminization complete and back on telescope
- 2019-02-11 - Start functional verification of two spectrographs at KPNO
- 2019-02-15 - Install second spectrograph on rack at Mayall Telescope
- 2019-03-11 - Fiber View Camera (FVC) installation (daylog)
- 2019-03-14 - Telescope motion enabled (daylog)
- 2019-03-20 - Imaging Surveys dr8b release
- 2019-04-01 - Start of Commissioning Instrument (CI) run (line 381)
Near-future milestones
- 2019-04-30 - Imaging Surveys DR8 release
- 2019-05-16 - End of CI run (6 weeks long)
- 2019-09-12 - Commissioning start with focal plane + spectrographs (First Light, line 691, "Telescope ready")
- 2019-10-01 - Last spectrograph installed (line 715, "Install Spectrographs")
- 2019-10-15 - Imaging Surveys DR9 release (TBD)
- 2019-12-02 - Initial Survey Validation fields (line 962)
- 2020-01-12 - Nominal start of Survey Validation (line 973)
Activities at Kitt Peak updated from DESI-4550 on 5 Apr 2019.