wiki:PublicPages/Schedule

Version 27 (modified by David Schlegel, 5 years ago) (diff)

--

Schedule

Past milestones

  • 2019-01-11 - Install first spectrograph on rack at Mayall Telescope
  • 2019-01-25 - Primary mirror re-aluminization complete and back on telescope
  • 2019-02-11 - Start functional verification of two spectrographs at KPNO
  • 2019-02-15 - Install second spectrograph on rack at Mayall Telescope
  • 2019-03-11 - Fiber View Camera (FVC) installation (daylog)
  • 2019-03-14 - Telescope motion enabled (daylog)
  • 2019-03-20 - Imaging Surveys dr8b release
  • 2019-04-01 - Start of Commissioning Instrument (CI) run
  • 2019-05-06 - Pause in CI run to move cage
  • 2019-05-15 - Resume CI run
  • 2019-06-03 - End of CI run

Near-future milestones

  • 2019-06-17 - Imaging Surveys DR8 release
  • 2019-10-07 - Commissioning start with focal plane + spectrographs (First Light, line 707, "Telescope ready")
  • 2019-10-29 - Last spectrograph installed (line 731, "Install Spectrographs")
  • 2019-10-15 - Imaging Surveys DR9 release (TBD)
  • 2019-12-24 - Initial Survey Validation fields (line 984)
  • 2020-01-12 - Nominal start of Survey Validation (line 995)

Activities at Kitt Peak updated from DESI-4550 on 15 June 2019.