Schedule
Past milestones
- 2019-01-11 - Install first spectrograph on rack at Mayall Telescope
- 2019-01-25 - Primary mirror re-aluminization complete and back on telescope
- 2019-02-11 - Start functional verification of two spectrographs at KPNO
- 2019-02-15 - Install second spectrograph on rack at Mayall Telescope
- 2019-03-11 - Fiber View Camera (FVC) installation (daylog)
- 2019-03-14 - Telescope motion enabled (daylog)
- 2019-03-20 - Imaging Surveys dr8b release
- 2019-04-01 - Start of Commissioning Instrument (CI) run
- 2019-05-06 - Pause in CI run to move cage
- 2019-05-15 - Resume CI run
- 2019-06-03 - End of CI run
- 2019-07-05 - Imaging Surveys DR8 release
Near-future milestones
- 2019-10-21 - Commissioning start with focal plane + spectrographs (First Light, line 738, "Telescope ready")
- 2019-11-26 - Last spectrograph installed (line 781, "Install Spectrographs")
- 2019-12-01 - Imaging Surveys DR9 release
- 2020-02-26 - End of commissioning, start of Survey Validation (4.5 months after line commissions start, from project plan in monthly report)
Activities at Kitt Peak updated from DESI-4550 on 21 Sep 2019. (start of SV taken from Monthly Report)