Changes between Version 16 and Version 17 of PublicPages/Schedule


Ignore:
Timestamp:
Mar 23, 2019 4:47:21 PM (6 years ago)
Author:
David Schlegel
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • PublicPages/Schedule

    v16 v17  
    99- 2019-03-11 - Fiber View Camera (FVC) installation   [https://desi.lbl.gov/trac/tracmailman/browser/private/desi-daylog/2019-March/000316.html (daylog)]
    1010- 2019-03-14 - Telescope motion enabled  [https://desi.lbl.gov/trac/tracmailman/browser/private/desi-daylog/2019-March/000320.html (daylog)]
     11- 2019-03-20 - Imaging Surveys dr8b release
     12
    1113
    1214== Near-future milestones ==
     
    1618- 2019-05-17 - End of CI run (6 weeks long, line 377)
    1719- 2019-07-15 - Imaging Surveys DR9 release
    18 - 2019-09-11 - Commissioning start with focal plane + spectrographs (First Light, line 632, "Telescope ready")
    19 - 2019-10-01 - Last spectrograph installed (line 656, "Install Spectrographs")
    20 - 2019-12-02 - Initial Survey Validation fields (line 904)
    21 - 2020-01-12 - Nominal start of Survey Validation (line 915)
     20- 2019-09-11 - Commissioning start with focal plane + spectrographs (First Light, line 673, "Telescope ready")
     21- 2019-10-01 - Last spectrograph installed (line 697, "Install Spectrographs")
     22- 2019-12-02 - Initial Survey Validation fields (line 945)
     23- 2020-01-12 - Nominal start of Survey Validation (line 956)
    2224
    23 Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 16 Mar 2019.
     25Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 20 Mar 2019.