Changes between Version 19 and Version 20 of PublicPages/Schedule


Ignore:
Timestamp:
Apr 8, 2019 10:22:07 AM (6 years ago)
Author:
David Schlegel
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • PublicPages/Schedule

    v19 v20  
    1515
    1616- 2019-04-30 - Imaging Surveys DR8 release
    17 - 2019-05-16 - End of CI run (6 weeks long, line 381)
    18 - 2019-09-16 - Commissioning start with focal plane + spectrographs (First Light, line 693, "Telescope ready")
    19 - 2019-10-01 - Last spectrograph installed (line 717, "Install Spectrographs")
     17- 2019-05-16 - End of CI run (6 weeks long)
     18- 2019-09-12 - Commissioning start with focal plane + spectrographs (First Light, line 691, "Telescope ready")
     19- 2019-10-01 - Last spectrograph installed (line 715, "Install Spectrographs")
    2020- 2019-10-15 - Imaging Surveys DR9 release (TBD)
    21 - 2019-12-03 - Initial Survey Validation fields (line 964)
    22 - 2020-01-12 - Nominal start of Survey Validation (line 975)
     21- 2019-12-02 - Initial Survey Validation fields (line 962)
     22- 2020-01-12 - Nominal start of Survey Validation (line 973)
    2323
    24 Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 1 Apr 2019.
     24Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 5 Apr 2019.