    1414== Near-future milestones ==
    1515
    16 - 2019-04-30 - Imaging Surveys DR8 release
    1716- 2019-05-16 - End of CI run (6 weeks long)
    18 - 2019-09-12 - Commissioning start with focal plane + spectrographs (First Light, line 691, "Telescope ready")
    19 - 2019-10-01 - Last spectrograph installed (line 715, "Install Spectrographs")
     17- 2019-05-31 - Imaging Surveys DR8 release
     18- 2019-09-12 - Commissioning start with focal plane + spectrographs (First Light, line 697, "Telescope ready")
     19- 2019-10-17 - Last spectrograph installed (line 732, "Install Spectrographs")
    2020- 2019-10-15 - Imaging Surveys DR9 release (TBD)
    21 - 2019-12-02 - Initial Survey Validation fields (line 962)
    22 - 2020-01-12 - Nominal start of Survey Validation (line 973)
     21- 2019-12-10 - Initial Survey Validation fields (line 980)
     22- 2020-01-12 - Nominal start of Survey Validation (line 991)
    2323
    24 Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 5 Apr 2019.
     24Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 28 Apr 2019.