    1919- 2019-06-17 - Imaging Surveys DR8 release
    20 - 2019-10-01 - Commissioning start with focal plane + spectrographs (First Light, line 707, "Telescope ready")
    21 - 2019-10-17 - Last spectrograph installed (line 731, "Install Spectrographs")
     20- 2019-10-07 - Commissioning start with focal plane + spectrographs (First Light, line 707, "Telescope ready")
     21- 2019-10-29 - Last spectrograph installed (line 731, "Install Spectrographs")
    2222- 2019-10-15 - Imaging Surveys DR9 release (TBD)
    23 - 2019-12-18 - Initial Survey Validation fields (line 983)
    24 - 2020-01-12 - Nominal start of Survey Validation (line 994)
     23- 2019-12-24 - Initial Survey Validation fields (line 984)
     24- 2020-01-12 - Nominal start of Survey Validation (line 995)
    2525
    26 Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 4 June 2019.