Changes between Version 27 and Version 28 of PublicPages/Schedule


Ignore:
Timestamp:
Jun 24, 2019 10:51:03 AM (6 years ago)
Author:
David Schlegel
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • PublicPages/Schedule

    v27 v28  
    1717== Near-future milestones ==
    1818
    19 - 2019-06-17 - Imaging Surveys DR8 release
    20 - 2019-10-07 - Commissioning start with focal plane + spectrographs (First Light, line 707, "Telescope ready")
    21 - 2019-10-29 - Last spectrograph installed (line 731, "Install Spectrographs")
     19- 2019-07-01 - Imaging Surveys DR8 release
     20- 2019-10-01 - Commissioning start with focal plane + spectrographs (First Light, line 712, "Telescope ready")
     21- 2019-10-29 - Last spectrograph installed (line 736, "Install Spectrographs")
    2222- 2019-10-15 - Imaging Surveys DR9 release (TBD)
    23 - 2019-12-24 - Initial Survey Validation fields (line 984)
    24 - 2020-01-12 - Nominal start of Survey Validation (line 995)
     23- 2019-12-18 - Initial Survey Validation fields (line 991)
     24- 2020-01-12 - Nominal start of Survey Validation (line 1002)
    2525
    26 Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 15 June 2019.
     26Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 22 June 2019.