    v3 v4  
    33== Near-future milestones ==
    44
    5 - 2019-01-10 - Primary mirror re-aluminization complete and back on telescope
    6 - 2019-01-17 - Fiber View Camera (FVC) installation
     5- 2019-01-14 - Primary mirror re-aluminization complete and back on telescope (line 269)
    76- 2019-01-28 - Begin installation of spectrographs + cryostats at the Mayall Telescope
    87- 2019-02-11 - Start functional verification of two spectrographs at KPNO
    98- 2019-02-15 - Imaging Surveys DR8 release
    10 - 2019-03-26 - Commissioning Instrument available to commissioning team (CI First Light)
    11 - 2019-05-06 - End of CI run (6 weeks long)
     9- 2019-02-28 - Fiber View Camera (FVC) installation (line 337)
     10- 2019-03-26 - Commissioning Instrument available to commissioning team (CI First Light, line 361)
     11- 2019-05-06 - End of CI run (6 weeks long, line 361)
    1212- 2019-07-15 - Imaging Surveys DR9 release
    13 - 2019-09-04 - Commissioning start with focal plane + spectrographs (First Light)
    14 - 2019-10-01 - Last spectrograph installed
     13- 2019-09-04 - Commissioning start with focal plane + spectrographs (First Light, line 582)
     14- 2019-10-01 - Last spectrograph installed (line 609)
    1515- 2020-01-11 - Nominal start of Survey Validation
    1616
    17 Activities at Kitt Peak updated from DESI-4550 on 16 Dec 2018.
     17Activities at Kitt Peak updated from DESI-4550 on 5 Jan 2019.