wiki:PublicPages/Schedule

Version 3 (modified by David Schlegel, 5 years ago) (diff)

--

Schedule

Near-future milestones

  • 2019-01-10 - Primary mirror re-aluminization complete and back on telescope
  • 2019-01-17 - Fiber View Camera (FVC) installation
  • 2019-01-28 - Begin installation of spectrographs + cryostats at the Mayall Telescope
  • 2019-02-11 - Start functional verification of two spectrographs at KPNO
  • 2019-02-15 - Imaging Surveys DR8 release
  • 2019-03-26 - Commissioning Instrument available to commissioning team (CI First Light)
  • 2019-05-06 - End of CI run (6 weeks long)
  • 2019-07-15 - Imaging Surveys DR9 release
  • 2019-09-04 - Commissioning start with focal plane + spectrographs (First Light)
  • 2019-10-01 - Last spectrograph installed
  • 2020-01-11 - Nominal start of Survey Validation

Activities at Kitt Peak updated from DESI-4550 on 16 Dec 2018.