    1818== Near-future milestones ==
    1919
    20 - 2019-10-21 - Commissioning start with focal plane + spectrographs (First Light, line 738, "Telescope ready")
    21 - 2019-11-26 - Last spectrograph installed (line 781, "Install Spectrographs")
     20- 2019-10-08 - Commissioning start with focal plane + spectrographs (First Light, line 744, "Telescope ready")
     21- 2019-11-26 - Last spectrograph installed (line 795, "Install Spectrographs")
    2222- 2019-12-01 - Imaging Surveys DR9 release
    2323- 2020-02-26 - End of commissioning, start of Survey Validation (4.5 months after line commissions start, from project plan in monthly report)
    2424
    25 Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 21 Sep 2019. (start of SV taken from Monthly Report)
     25Activities at Kitt Peak updated from [docdb:4550 DESI-4550] on 28 Sep 2019. (start of SV taken from Monthly Report)