Schedule
Near-future milestones
- 2018-12-20 - Primary mirror back on telescope
- 2019-01-17 - FVC install
- 2019-01-28 - CEA and Pat Jelinsky traveling to KPNO to install cryos (3 weeks)
- 2019-02-11 - Start functional verification of 2 spectrographs at KPNO
- 2019-02-15 - DR8 release
- 2019-03-11 - CI installed
- 2019-03-14 - CI available to commissioning team
- 2019-04-24 - End of CI run (6 weeks long)
- 2019-07-15 - DR9 release
- 2019-08-23 - Focal plane + fiber installation
- 2019-09-03 - Commissioning start
- 2019-10-01 - Last spectrograph installed
- 2020-01-11 - Nominal start of SV
Activities at Kitt Peak updated from DESI-4550 on 11 Dec 2018.