Version 2 (modified by 6 years ago) (diff) | ,
---|
Schedule
Near-future milestones
- 2018-12-20 - Primary mirror re-aluminization complete and back on telescope
- 2019-01-17 - Fiber View Camera (FVC) installation
- 2019-01-28 - Begin installation of spectrographs + cryostats at the Mayall Telescope
- 2019-02-11 - Start functional verification of two spectrographs at KPNO
- 2019-02-15 - Imaging Surveys DR8 release
- 2019-03-11 - Commissioning Instrument (CI) installed
- 2019-03-14 - Commissioning Instrument available to commissioning team
- 2019-04-24 - End of CI run (6 weeks long)
- 2019-07-15 - Imaging Surveys DR9 release
- 2019-08-23 - Focal plane + fiber installation
- 2019-09-03 - Commissioning start
- 2019-10-01 - Last spectrograph installed
- 2020-01-11 - Nominal start of Survey Validation
Activities at Kitt Peak updated from DESI-4550 on 11 Dec 2018.