Changes between Version 1 and Version 2 of PublicPages/Schedule


Ignore:
Timestamp:
Dec 12, 2018 2:58:47 PM (5 years ago)
Author:
David Schlegel
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • PublicPages/Schedule

    v1 v2  
    33== Near-future milestones ==
    44
    5 - 2018-12-20 - Primary mirror back on telescope
    6 - 2019-01-17 - FVC install
    7 - 2019-01-28 - CEA and Pat Jelinsky traveling to KPNO to install cryos (3 weeks)
    8 - 2019-02-11 - Start functional verification of 2 spectrographs at KPNO
    9 - 2019-02-15 - DR8 release
    10 - 2019-03-11 - CI installed
    11 - 2019-03-14 - CI available to commissioning team
     5- 2018-12-20 - Primary mirror re-aluminization complete and back on telescope
     6- 2019-01-17 - Fiber View Camera (FVC) installation
     7- 2019-01-28 - Begin installation of spectrographs + cryostats at the Mayall Telescope
     8- 2019-02-11 - Start functional verification of two spectrographs at KPNO
     9- 2019-02-15 - Imaging Surveys DR8 release
     10- 2019-03-11 - Commissioning Instrument (CI) installed
     11- 2019-03-14 - Commissioning Instrument available to commissioning team
    1212- 2019-04-24 - End of CI run (6 weeks long)
    13 - 2019-07-15 - DR9 release
     13- 2019-07-15 - Imaging Surveys DR9 release
    1414- 2019-08-23 - Focal plane + fiber installation
    1515- 2019-09-03 - Commissioning start
    1616- 2019-10-01 - Last spectrograph installed
    17 - 2020-01-11 - Nominal start of SV
     17- 2020-01-11 - Nominal start of Survey Validation
    1818
    1919Activities at Kitt Peak updated from DESI-4550 on 11 Dec 2018.