5 | | - 2018-12-20 - Primary mirror back on telescope |
6 | | - 2019-01-17 - FVC install |
7 | | - 2019-01-28 - CEA and Pat Jelinsky traveling to KPNO to install cryos (3 weeks) |
8 | | - 2019-02-11 - Start functional verification of 2 spectrographs at KPNO |
9 | | - 2019-02-15 - DR8 release |
10 | | - 2019-03-11 - CI installed |
11 | | - 2019-03-14 - CI available to commissioning team |
| 5 | - 2018-12-20 - Primary mirror re-aluminization complete and back on telescope |
| 6 | - 2019-01-17 - Fiber View Camera (FVC) installation |
| 7 | - 2019-01-28 - Begin installation of spectrographs + cryostats at the Mayall Telescope |
| 8 | - 2019-02-11 - Start functional verification of two spectrographs at KPNO |
| 9 | - 2019-02-15 - Imaging Surveys DR8 release |
| 10 | - 2019-03-11 - Commissioning Instrument (CI) installed |
| 11 | - 2019-03-14 - Commissioning Instrument available to commissioning team |