    33== Near-future milestones ==
    44
    5 - 2018-12-20 - Primary mirror re-aluminization complete and back on telescope
     5- 2019-01-10 - Primary mirror re-aluminization complete and back on telescope
    66- 2019-01-17 - Fiber View Camera (FVC) installation
    77- 2019-01-28 - Begin installation of spectrographs + cryostats at the Mayall Telescope
    88- 2019-02-11 - Start functional verification of two spectrographs at KPNO
    99- 2019-02-15 - Imaging Surveys DR8 release
    10 - 2019-03-11 - Commissioning Instrument (CI) installed
    11 - 2019-03-14 - Commissioning Instrument available to commissioning team
    12 - 2019-04-24 - End of CI run (6 weeks long)
     10- 2019-03-26 - Commissioning Instrument available to commissioning team (CI First Light)
     11- 2019-05-06 - End of CI run (6 weeks long)
    1312- 2019-07-15 - Imaging Surveys DR9 release
    14 - 2019-08-23 - Focal plane + fiber installation
    15 - 2019-09-03 - Commissioning start
     13- 2019-09-04 - Commissioning start with focal plane + spectrographs (First Light)
    1614- 2019-10-01 - Last spectrograph installed
    1715- 2020-01-11 - Nominal start of Survey Validation
    1816
    19 Activities at Kitt Peak updated from DESI-4550 on 11 Dec 2018.
     17Activities at Kitt Peak updated from DESI-4550 on 16 Dec 2018.